Pile Load Test
Pile load test is the most acceptable method to determine
the load carrying capacity of a pile. The load test may be carried out either
on a driven pile or cast in situ piles. The test can be made either on a single
pile or on a group of piles. Before
finalizing the design, load tests are carried out on piles installed for the
purpose on the site. These are called initial load tests. They are useful in
determining the general suitability of the proposed pile foundation, comparing
the load capacity obtained from formulae, and for a general check on the piling
equipment to be used as well as on soil properties.
Purpose of Pile load test is:
·
To determine settlement under working load.
·
To determine ultimate bearing capacity.
·
To ascertain as a proof of acceptability.
In general
two types of pile load tests are conducted:
·
Initial Test: It is performed before the start
of construction, to access the design adequacy. In initial test the test load
is about 2.5 times the design load.
·
Routine Test: It is performed during the working
time. In this test the test load is about 1.5 times the design load
There are
two methods of testing piles
- Maintained Load Test: Maintained Load test is the better method. This method provides an idea of both shaft and end resistance. In this method the contribution of each soil layer can be calculated but it is time consuming. The failure load is not clearly defined. In this method the distance of anchor piles from test pile should not be less than 1.5 m.
Process of Load application
·
Load is applied in increment at the rate of 25 %
of design load till working load is reached.
·
For each load increment, load constant must be
maintained till settlement according to code.
·
Go for next Loading
·
After working load is reached, hold the load for
24 hour and record hourly settlement and unload.
·
Reload from working load to higher load.
The ultimate
load is determined by plotting the load settlement curve.
1.
2. Constant Rate Penetration Test: This test is most suitable for friction pile.
In this test, the well defined failure load is obtained and the method is very
quick. However, this method doesnot provide elastic settlement at working load.
In this method the pile is jacked continuously into soil at constant rate till
failure takes place. The jacking rate in clay is 0.75 mm/min and a small
movement required for failure. In sands, the jacking rate is 5mm/min and large
movement is required for failure.
The failure load is that at which the rate of
settlement continues undiminished without further increment of load. It is the
load where the load settlement curve has its minimum radius of curvature. The
ultimate load is taken as the abscissa of the point of intersection of tangents
of initial and final portion of the load settlement curve.
Comments
Post a Comment